FB6 05 Steiner

Embed Size (px)

Citation preview

  • 7/29/2019 FB6 05 Steiner

    1/8

    STEINER, EDLMAIR AND VERGEINER: PIPE-JACKING VERSUS CONVENTIONAL TUNNELLING

    FELSBAU 23 (2005) NO. 6 27

    PIPE

    JACKING

    Pipe-Jacking versus

    Conventional TunnellingConfrontation of both methods at the CableTunnel System Graz Main Railway Station

    By Helmut Steiner, Gerald Edlmair and Ralf Vergeiner

    Rohrvorpressung oder NT-Vortrieb Gegenberstellung der beiden Vortriebsmethodenam Beispiel des Leitungskollektorensystems GrazHauptbahnhof

    Der steigende Bedarf an Kabelwegen im Bereich des Gra-zer Hauptbahnhofs machte es erforderlich, unter den be-

    stehenden Gleisanlagen einen kontinuierlich aufgefahre-nen Lngskollektor (Rohrvorpressung DN 3 180 mit offe-nen Haubenschild, Lnge 877 m) und einen rechtwinkeligdavon abzweigenden, zyklisch vorgetriebenen Querkollek-tor (Lnge 85 m) zu errichten. Diese Vortriebe wurden beiberdeckungen von 3 bis 14 m in den wrm-glazialen Te-rassenschottern des Grazer Felds ausgefhrt.

    Da die beiden Vortriebsmethoden unter gleichen bezie-hungsweise hnlichen Untergrund- und nahezu identi-schen Querschnittsverhltnissen (etwa 12 bis 13 m2 Aus-

    bruchquerschnitt) zur Anwendung kamen, war es ab-

    schlieend mglich, vergleichende Betrachtungen hin-sichtlich technischer und wirtschaftlicher Gesichtspunktedurchzufhren.

    Spezielles Augenmerk wird auf den Vergleich zwischenden vorab gettigten Prognosen und den vor Ort angetrof-fenen Verhltnissen und den dabei gemachten Erfahrun-gen gelegt. Die Aspekte Vortriebsleistung und Bauzeit-vergleich, Oberflchensetzungen und die Auswirkungen

    auf den Bahnbetrieb, Vortriebskosten, allgemeine Sicher-heitsbetrachtungen werden nher betrachtet und Ver-gleiche zwischen den beiden unterschiedlichen Vortriebs-methoden gezogen.

    The increasing infrastructure requirements of Graz main

    railway station required a longitudinal Main Cable Tunnel

    with 877 m in length and driven with pipe jacking by in-stalling precasted concrete pipes and utilizing an open

    hooded shield (3.18 m internal diameter) for excavation.

    The Cross Cable Tunnel (85 m length) was driven by con-

    ventional excavation utilizing NATM support and a final

    shotcrete lining. The headings of the two tunnels had to be

    driven through quaternary sediments above the ground

    water table with an overburden varying from 3 to 14 m.

    As both excavation methods were carried out with simi-

    lar cross sections (approximately 12 to 13m2 excavation

    section) and under similar ground conditions, a reliable

    comparison of both methods is possible. The paper includes

    technical and economical aspects, with the main focus on

    the comparison between prognosis and encountered condi-

    tions. Additionally following aspects like rates of advance

    and construction time, surface settlements and their effect

    on the railway operation, construction costs as well as gen-

    eral safety aspects are worked out and compared between

    the two different tunnelling methods.

    The upgrading of the existing railway proper-ties of Graz Main Railway Station and there-fore the increasing infrastructure requirements

    necessitate new data and power links. Addition-

    ally, the existing southbound railway line Sd-

    bahn, the regional railway to Kflach and the

    new Koralmbahn Graz Klagenfurt will also

    be integrated to the existing and new facilities.The main cables are 15 kV traction power and

    110 kV high voltage supply cables and multitudi-

    nous links for the railway control systems like

    data and telephone cables. Due to the dense ar-

    rangement of the existing facilities on the surface,

    such as railway tracks, buildings, platforms, a

    shallow placement of the cables was impossible.

    Therefore an underground solution with two

    different orientated tunnels was designed, which

    was later on constructed during unrestricted

    railway operation at the Graz central station.

    These structures consist of the 877 m longitudi-

    nal Main Cable Tunnel, the 85 m Cross CableTunnel, three access shafts, several cable ducts

    to existing facilities and an underground connec-

    tion between the cross tunnel and the basement

    of the station building (Figures 1, 2, 11 and 12).

    Description of bothtunnelling methods

    During preparation of the final design a conven-

    tional tunnelling method and a shield tunnelling

    method were considered. The costs for both

    methods were estimated to be similar. Hence it

    was decided to prepare tender documents forboth methods (4). The tenderer could either se-

    lect one of the two methods or bid for both meth-

    ods. Additionally the tender documents also con-

    tained specifications for alternative offers.

    Cross sectionThe cross section was designed to meet the re-

    quirements of a clearance profile of 1 m width

    and 2.1 m height, twelve cable trays on the walls

    and three cable ducts in the invert for 15 and 110

    kV power cables (Figure 3).

    Excavation methodsThe excavation equipment had to be suitable for

    the geological situation with quaternary sandy

    gravel, silty gravel, silt and sand lenses, occa-

    sionally stones/blocks up to several dm diameter

  • 7/29/2019 FB6 05 Steiner

    2/8

    28

    PIPE

    JACKING

    STEINER, EDLMAIR AND VERGEINER: PIPE-JACKING VERSUS CONVENTIONAL TUNNELLING

    FELSBAU 23 (2005) NO. 6

    Fig. 2 Top view detailof the Main and the

    Cross Cable Tunnel.

    Bild 2 Luftbilddetaildes Lngs- undQuerkollektors.

    Fig. 1 Top view

    of the Cable TunnelSystem Graz MainRailway Station.

    Bild 1 Luftbild desLeitungskollektoren-Systems am GrazerHauptbahnhof.

    Fig. 3 Cross sec-

    tions for conventionaltunnelling and in case

    of shield excavation.

    Bild 3 Regelquer-schnitte fr zyklischen

    und kontinuierlichenVortrieb.

  • 7/29/2019 FB6 05 Steiner

    3/8

    STEINER, EDLMAIR AND VERGEINER: PIPE-JACKING VERSUS CONVENTIONAL TUNNELLING

    FELSBAU 23 (2005) NO. 6 29

    PIPE

    JACKING

    Fig. 4 Schematicallylongitudinal and cross

    section for conven-

    tional tunnelling.

    Bild 4 SchematischerLngs- und Quer-

    schnitt den zyklischenVortrieb betreffend.

    Fig. 5 Supportingworks at conventionaldrive.

    Bild 5 Sicherungs-

    arbeiten beim zykli-schen Vortrieb.

    Fig. 6 Schematicallylongitudinal sectionthrough the openhooded shield.

    Bild 6 Schema-tischer Lngenschnittdurch das offeneHaubenschild.

    so called Murnockerl and maybe local are-

    as with conglomerates (6). Also further anthro-

    pogenic material in areas with low overburden

    and the possibility of relics from the 2nd world

    war had to be considered. As the ground water

    table is below the tunnel, only seepage water

    was expected.

    For conventional excavation a intersection

    of the cross section in the upper top heading

    section and the combined bench/invert section

    was foreseen. The maximum distance between

    tunnel face and invert closure was defined to

    be less than 4 m (Figures 4 and 5). The surface

    settlements were estimated to be less than

    10 mm.

    The shield construction applied was an open

    hooded shield (1). The accessibility of the tunnel

    face was a precondition for the method in order

    to remove anthropogenic material upon re-

    quirement. The basic design parameters of the

    shield are 72 inclined cutting edge, a longitudi-

    nal cutting head, three forepoling blades in the

    roof section, three breasting plates to support

    the upper face section and a horizontal intersec-

  • 7/29/2019 FB6 05 Steiner

    4/8

    30

    PIPE

    JACKING

    STEINER, EDLMAIR AND VERGEINER: PIPE-JACKING VERSUS CONVENTIONAL TUNNELLING

    FELSBAU 23 (2005) NO. 6

    Fig. 8 Shield drive performance per day and net shield drive performance per hour.

    Bild 8 Schildvortriebsleistungen pro Tag und netto Schildvortriebsleistungen proStunde.

    tion of the face called table (Figures 6 and 7).

    The expected surface settlement in case of

    shield excavation was between 20 and 30 mm.

    Tunnel liningFor conventional tunnelling a single shell shot-

    crete lining, thickness 0.25 m, lattice girders and

    two layers of wire mesh were designed. As there

    were no special requirements concerning even-ness and water tightness of the cable tunnel, no

    final lining was necessary.

    In case of shield excavation a segmental lin-

    ing, thickness 0.25 m, was defined in the tender

    documents. Within the alternative tender the

    segmental lining was replaced by precasted con-

    crete pipes with 3.68 m outer diameter, 3.2 m

    length, 0.25 m thickness and 21.8 t weight (2, 3).

    ForepolingThe forepoling for conventional tunnelling was

    designed by the use of steel sheets (t = 5 mm,L = 2 to 2.5 m, b = 0.22 m, up to 30 pcs) or fore-

    poling piles (d = 26 mm, L = 2.3 to 3.5 m, 25 to

    40 pcs). The decision weather to use sheets or

    piles was made on site, depending on the soil

    density (see Figures 4 and 5).

    The shield was equipped with three blades in

    the roof section which were set with hydraulic

    jacks with a maximum stroke of 0.6 m (see Fig-

    ure 6).

    Face stabilityThe face stability for conventional tunnelling

    was ensured by intersection of the cross sectionin the upper top heading section and the com-

    bined bench/invert section, a supporting core

    and further face support by shotcrete and wire

    mesh (see Figures 4 and 5).

    In case of shield excavation the inclined tun-

    nel face (between 40 and 72), the horizontal

    intersection (table) to create an upper support

    body of ground material and the three breasting

    plates for face support in case of a longer exca-

    vation stop, guaranteed the face stability (see

    Figures 6 and 7).

    Additional measures aheadof excavation works

    Experience shows that within the well graded

    soil, sometimes lenses of non-cohesive rounded

    gravel occur. Though these gravels were not en-

    countered within the site investigation pro-

    gramme, their existence had to be expected. Uni-

    form sized layers could have a non-cohesive

    flowing behaviour and might jeopardize the sta-

    bility of the tunnel face.

    As a precautionary measure grouting ahead

    of the tunnel face was carried out. Within the

    design of the conventional excavation method,

    grouting was foreseen by means of 6 m grouting

    lances. The lances are set every second round

    and grouted with low pressure to improve the

    abutment area of the forepoling.

    Fig. 7 View through the open shield to the excavation face.

    Bild 7 Blick durch das offene Schild in Richtung Ortsbrust.

  • 7/29/2019 FB6 05 Steiner

    5/8

    STEINER, EDLMAIR AND VERGEINER: PIPE-JACKING VERSUS CONVENTIONAL TUNNELLING

    FELSBAU 23 (2005) NO. 6 31

    PIPE

    JACKING

    Fig. 9 Detail of theexcavation face with

    partly solidified soilby grouting material Mixed Face Condi-

    tions.

    Bild 9 Detail derOrtsbrust mit teilweise

    durch Injektionsgutverfestigtem Boden.

    For shield excavation the underground grout-

    ing by use of lances out of the shield was estimat-

    ed to be not economical because it would slow

    down the advance rate in a significant degree.

    Hence it was decided to carry out grouting meas-

    ures from the surface. Expected problems were

    the spoiling of railway ballast substructure with

    grout and the interference of the grouting works

    with the railway operation.

    Estimated advance ratesThe advance rates for conventional tunnelling

    were estimated to be between 2.5 and 3.5 m per

    day. For shield excavation the rates were esti-

    mated to be about 8 m/d. Due to the lower ad-

    vance rates for conventional tunnelling two

    drives would be necessary to meet the time

    schedule.

    Additional safety measures

    World War II relicsGraz Central Station and the nearby factories

    were subject to heavy bombing in the years 1944

    to 1945 (5). Experience shows an percentage of

    about 10 to 15 % of the bombs were duds. Sever-

    al areas and points were traced by the depart-

    ment of civil defence in Graz where duds were

    thought to be. As these areas covered nearly the

    whole project area, it was decided to carry out a

    systematic exploration by means of a magnetic

    field probe. With this method three possible

    points were traced and later on explored by

    means of test pits. One of the pits contained a

    500 kg dud, which was deactivated by an expertfrom the ministry of the interior.

    Monitoring

    The monitoring for conventional tunnelling con-

    sisted of deformation measurements of shotcrete

    lining and of ground and track settlements. The

    monitoring for shield excavation consisted only

    of surface measurements of ground and track

    settlements. In both cases the inclination of rail-

    way catenary masts in critical excavation phases

    are monitored around the clock.

    Conditions and excavationvelocity at the longitudinalMain Cable Tunnel

    According to the Austrian Flexible Model of

    Construction Time the average mechanical tun-

    nel drive had been offered by the contractor with

    a daily rate of 9.5 m. This rate already included

    the launching of the tunnelling machine, all cal-

    culated interruptions due to the working proc-

    ess, geological problems, predicted downtimes,

    reinstalling of the machinery and the refilling of

    the ring space. The real net tunnelling advance

    was calculated by the contractor with approxi-

    mately 17 m/d.

    The daily excavation works were carried out

    on a 24 hour basis, three shifts eight hours each.

    The first days were embossed by a very slow ad-

    vance because equipment like the conveyor belthad to be installed simultaneously. But after a

    few days, on the 1st of October 2004 the excava-

    tion velocity reached the overall peak with

    23 m/d due to favourable geological conditions

    and short mucking times (Figure 8).

    From chainage 230 m on increasing jacking

    pressures up to a level of over 500 bar and prob-

    ably also the bended lining at the area of the

    Middle Shaft led to much lower advance rates

    than before. Around the 18th of November 2004

    the shield advance reached again peak values up

    to 22 m/d although the mucking distance was

    fairly long (approximately 650 m). It seemed thatat this part of the drive the excavation crew got

    used to the driving conditions, which could be

    interpreted as learning curve. The late rising of

    the learning curve is probably the result of unex-

    pected unfavourable face conditions and that the

    jacking pressures were on their limit. Finally on

    6th of December 2004 the shield reached suc-

    cessfully the target shaft north.

    It was intended to create a more or less homo-

    geneous injection umbrella along the whole tun-

    nel roof by drilling injection pipes in a certain

    grid with following grouting. During excavation

  • 7/29/2019 FB6 05 Steiner

    6/8

    32

    PIPE

    JACKING

    STEINER, EDLMAIR AND VERGEINER: PIPE-JACKING VERSUS CONVENTIONAL TUNNELLING

    FELSBAU 23 (2005) NO. 6

    Fig. 11 Longitudinal section of the Main Cable Tunnel including geology and vertical settlements.

    Bild 11 Schnitt durch den Lngskollektor Darstellung der Geologie und der Setzungen.

    it was visible that wide areas around the roof

    were not injected because of the compactness of

    the ground. But also loose gravel layers were

    encountered uninjected possibly due to a too

    wide drilling grid (Figure 9). Unexpected chang-

    ing of the ground compactness led to a reduction

    of the drive velocity as well as the above average

    maintenance times. Also the bentonite slurry

    used as a lubricant film around the jacking pipes

    could not built up properly due to permeable

    gravel layers in the quaternary sediments. The

    effects of this behaviour were high jacking pres-

    sures due to the high friction between the con-crete pipes and the surrounding soil.

    Maintenance and downtimes calculated by

    the contractor have been exceeded significantly

    (7).

    Fig. 10 Theoreticalcomparison of con-struction time between

    shield and conven-tional excavation atthe Main Cable Tunnel.

    Bild 10 TheoretischerBauzeitvergleich

    zwischen zyklischemund kontinuierlichemVortrieb beim Lngs-kollektor.

    Conditions and excavationvelocity at the mined CrossCable Tunnel

    The mined tunnel part of this project could be

    finished without any problems, except for steel

    lagging problems at one short part of the tunnel

    due to big stones in the tunnel perimeter. After

    changing steel lagging to forepoling piles no fur-ther problems were encountered.

    Because of the very small tunnel profile and

    the very short learning time for the tunnel crew

    the average driving performance was approxi-

    mately 3 m/d.

    Comparison of theexcavation velocities

    A theoretical comparison of the overall construc-

    tion time based on the actual advance rates

    shows, that two conventional drives (north andsouth) for the longitudinal Main Cable Tunnel,

    would have shown the same construction time as

    a shield drive (approximately 180 d). Manufac-

    turing time as for the shield was not needed in

    the case of conventional tunnelling which had

    positive effects on construction time (Figure 10).

    Settlements

    Settlements encountered at thelongitudinal Main Cable Tunnel

    From the beginning of excavation it had to be

    learned that the geological conditions changedsuddenly in an unpredictable way. The geotech-

    nical safety management plan has foreseen that

    the normal settlement values would not exceed

    10 mm. The 1st level alert criterion was reached

  • 7/29/2019 FB6 05 Steiner

    7/8

    STEINER, EDLMAIR AND VERGEINER: PIPE-JACKING VERSUS CONVENTIONAL TUNNELLING

    FELSBAU 23 (2005) NO. 6 33

    PIPE

    JACKING

    Fig. 12 Longitudinal

    section of the CrossCable Tunnel including geology andvertical settlements.

    Bild 12 Schnitt durch

    den Querkollektor Darstellung derGeologie und der

    Setzungen.

    by exceeding 10 mm surface settlements at the

    driving area and 20 mm 10 m behind the face.

    The 2nd level alert criterion has been triggered by

    reaching 50 mm and the 3rd criterion by exceed-

    ing 50 mm and posing effects to the safety of peo-

    ple or structures.

    Sudden inrushes of mostly loose gravel always

    triggered the 3rd level alert criterion. Fortunately

    these occurrences did not effect the surface im-

    mediately. Volume losses in front of the excava-

    tion face spread slowly within one to two days to

    the surface, depending on the overburden. Sothere was always enough time to inform the

    management of Graz Main Station. The average

    settlements had been measured with 40 to

    60 mm at the area of overburden between 3.5

    and 7.5 m (Figure 11). Afterwards the volume

    losses had to be filled up with cement grout from

    the surface to prevent further settlements and

    the tracks had to be readjusted by a ballast

    tamping machine.

    Settlements encounteredat the Cross Cable Tunnel

    The same alert level criteria were valid for the

    cross passage, excavated by conventional min-

    ing technique. By using forepoling items like

    steel lagging and forepoling piles volume losses

    could be prevented when passing difficult geo-

    logical conditions. The maximum settlements at

    the surface have been measured with 9 mm,

    which did not really effect the railway tracks

    (Figure 12). The excavation of the cross passage

    could be finished without interruption of the

    train sequence above.

    Comparison of settlementsAt comparable tunnel sections by shield driving

    and by conventional tunnelling with similar

    overburden and geology one can clearly see adifference on the surface effects between the two

    methods. Similar areas are for the Main Cable

    Tunnel from tunnel metre 510 to the end of the

    drive (tunnel metre 877) and for the cross pas-

    sage from the beginning to the end. Both zones

    have been excavated with overburdens from 3.5

    to approximately 7.5 m.

    Primary settlements

    Whereas the excavation of the cross passage

    could be finished without interruption of the reg-

    ular train operation, settlements above the

    shield drive led to continued interruption of train

    service on tracks above. The maximum vertical

    surface displacements have been measured with

    only 9 mm at the cross passage area. The peak

  • 7/29/2019 FB6 05 Steiner

    8/8

    34

    PIPE

    JACKING

    STEINER, EDLMAIR AND VERGEINER: PIPE-JACKING VERSUS CONVENTIONAL TUNNELLING

    FELSBAU 23 (2005) NO. 6

    value of settlements at the shield driving area

    was more than 200 mm, the average between 40

    and 60 mm.

    Secondary consolidation

    Whereas the secondary consolidation stopped

    immediately after ring closure at the mined tun-

    nel part, the consolidation above the shield drive

    kept on for weeks. The bulking of the surround-ing soil caused by volume loss during shield drive

    led to excessive secondary consolidation. Three

    month after penetrating shaft north end of

    shield drive the average was measured with

    8 mm at the area mentioned above.

    Working conditionsfor the tunnel crew

    Shield driveThe soils encountered usually during the shield

    drive had a constant humidity so that no dustcould develop. The shielded space showed ex-

    cellent air conditions for the tunnelling crew

    during the whole drive and also the staffs ac-

    cess to the shield was mostly dry and clean. Al-

    though sudden inrushes of soil into the shield

    occurred, the staffs health and safety were

    never at risk due to the sufficient distance be-

    tween the machine driver and the excavation

    face.

    Conventional tunnellingDue to small portions to be supported step by

    step this could only be managed by applicationof dry shotcrete. During spraying and signific-

    ant time after the small tunnel profile was still

    full with dust although the tunnel was ventilat-

    ed. Especially to the nozzle man the situation

    was quite uncomfortable because of very re-

    duced visibility during placing the shotcrete.

    The stability of the tunnel itself was never in

    danger.

    Theoretical comparisonof excavation costs

    A retrospective comparison show similar costs

    of about 5 100 EUR per metre for both methods.

    The sum includes tunnelling costs, costs for

    shield and mining equipment, cost for site facil-

    ities, time related cost, cost for muck transport,

    costs for surface grouting and costs for explora-

    tion on war legacies.

    Summary

    According to construction costs and time there is

    no significant difference between the two meth-

    ods. However a glance at surface settlements

    and its effects on railway operation gives the

    mined method conventional tunnelling a

    clear preference for projects with similar bound-

    ary conditions in the future. The constant threatof surface instability above the tunnel drive

    caused by potential sudden inrushes of ground

    material is unfavourable for a reliable safety

    management on site.

    The comparison resumes as follows:

    Similar costs per metre,

    Similar total construction time, considering

    preparation time, maintenance time and

    downtime,

    Absolute advantage for the conventional

    method concerning surface settlements. The

    surface settlements of the conventional meth-od add up to only 10 to 20 % of the shield

    drive,

    Absolute advantage for the conventional

    method concerning the face stability and the

    minimization of interference on the railway

    structures,

    Absolute advance for the shield method con-

    cerning the working conditions for the tunnel

    crew,

    Advance for the shield method for the later

    maintenance and equipment installations in

    the cable tunnels due to the perfect even

    shaped concrete surface.

    References

    1. Steiner, H. ; Vigl, A. ; Vergeiner R. ; Hrlein N.: Leitungs-kollektor Graz Hbf. Pressrohrvortrieb DN 3180 mit offe-

    nem Haubenschild. Felsbau 23 (2005) Nr.5, S.76-82.2. Hrlein, N. ; Ppperl, R. ; Steiner, H. ; Schneider, K.: DerKabelkollektor Graz Hauptbahnhof. Beton Zement 4/2004,S. 42-45.3. Kolic, D. ; Hrlein, N. ; Schneider, K. ; Steiner H.: Com-

    petitiveness of Pipe-Jacking Tunnels. Symposium KeepConcrete Attractive, Budapest 2005.4. Fischer, P. ; Bauer, F.:Zuschlagskriterien zur Beurteilungvon Alternativangeboten am Beispiel des Wienerwald Tun-

    nels. Tagungsband sterreichischer Tunneltag 2004,

    S. 87-90.5. Brunner, W.: Bomben auf Graz. Die DokumentationWeissmann. Graz: Leykam Verlag, 1989.6. sterreichische Bundesbahnen: Baugeologische Do-

    kumentation und Vortriebsbetreuung des Leitungskollek-

    tors Graz Hbf. Mag. Erhard Neubauer ZT GmbH, 2005 (in-tern).7. sterreichische Bundesbahnen: Geotechnische Doku-

    mentation Leitungskollektors Graz Hbf. iC consulten, 2005(intern).

    Authors

    Dipl.-Ing. Dr. mont. Helmut Steiner, BB-Infrastruktur BauAG, Geschftsbereich Projekte, Projektleitung Koralm-bahn 1, Griesgasse 11 / 2. Stock, A- 8020 Graz, Austria,E-Mail [email protected]; Dipl.-Ing. Gerald Edlmair,Laabmayr & Partner, Preishartlweg 4, A-5020 Salzburg ,Austria, E-Mail [email protected]; Dipl.-Ing. Ralf Vergeiner,

    iC consulenten, Kaiserstrae 45, A-1070 Vienna, Austria,E-Mail [email protected]

    www.vge.de