    Your Role: You are a manager for RiceUtility Production, and you missed themeeting with the consultants design team.Youve been given their PowerPoint file.

    You have to let the other two managers onthe committee know what you think of theproposed design.

    Sample Chemical Engineering

    Student Team PowerPoint forAnalysis

  • 7/28/2019 Aceton Plant

    2/25

    Note: Throughout, orange slides like thisone will ask you questions to help you pickout things you want to remember about

    designing team PowerPoints.For more help or background information:Making Logical Technical

    Arguments PPT; Team Presentations in Chemical and BiomolecularEngineering PPT

    Sample Chemical Engineering

    Student Team PowerPoint forAnalysis

  • 7/28/2019 Aceton Plant

    3/25

    Acetone Production PlantDesign

    December 2, 20__

    Student Team AFrom Ace Consultants

  • 7/28/2019 Aceton Plant

    4/25

    Project Motivation

    Rice UP - acetone requirement for

    increased Anphal production

    Maintain ROI at higher production rate

  • 7/28/2019 Aceton Plant

    5/25

    Project Goals

    Increase Acetone Production by 30%

    Minimize Plant Costs

    Operating costs

    Additional capital purchasing costs

  • 7/28/2019 Aceton Plant

    6/25

    . eac or an r pp ng o umn1. Reactor and Stripping Column

    1. Reactor and Stripping Column

  • 7/28/2019 Aceton Plant

    7/25

    Sample Chemical EngineeringStudent Team PowerPoint for

    Analysis

    What was the point of the processflow diagram you just saw? Is thisthe teams recommendeddesign?

    What is the team trying to tell youabout their work?

    Are you impressed by their designso far? Why is it good?

    Go back for a second look.

    What should the heading be?

    In regard to the previous slide:

  • 7/28/2019 Aceton Plant

    8/25

    2. Acetone Purification

  • 7/28/2019 Aceton Plant

    9/25

    3. Isopropyl Alcohol Recovery Column

  • 7/28/2019 Aceton Plant

    10/25

    Process Specifications

    99.9% Pure Acetone

    90% Pure Hydrogen

    TOC

  • 7/28/2019 Aceton Plant

    11/25

    Cost Analysis

    $243,000 /yr profit from given base case

    ~1 per pound of acetone product profitmargin

  • 7/28/2019 Aceton Plant

    12/25

    If these are the specifications, what

    criteria will you be looking for in the

    teams design?

    What does the team need to show you

    to convince you the design will do

    what is needed?

    Did the team meet these requirements

    in its design solution? How do you

    know?

    In regard to the previous slide:

  • 7/28/2019 Aceton Plant

    13/25

    Modeling Issue

    UNIFAC VLE Model does not accuratelypredict x-y diagram at high acetoneconcentrations

    NRTL is best property package foracetone/water binary system

    Based on DeChema VLE data

  • 7/28/2019 Aceton Plant

    14/25

    Options

    1) Use extractive distillation methods

    2) Purchase 39MM lb acetone (openmarket)

    3) Produce 97.6% acetone

  • 7/28/2019 Aceton Plant

    15/25

    1) Extractive Distillation

    3 Solvents 1,2 dimethoxyethane (Diglyme)

    Acetonitrile

    N-Methylpyrrolidone (NMP)

    Case Study: Diglyme

    Prohibitive Cost $6.765 MM /yr to purchase Diglyme

    Additional Column

  • 7/28/2019 Aceton Plant

    16/25

    How do you know the cost of extractivedistillation Is prohibitive?

    Why is the Diglyme case of interest?

    Is an additional column a solution orpart of the cost?

    Is extractive distillation theh usualmethod of making acetone?

    In regard to the previous slide:

  • 7/28/2019 Aceton Plant

    17/25

    2) Purchase Acetone

    Purchase 39 MM lb per year acetone for$10.92 MM

    Shut down acetone production

    Minimize investment losses

  • 7/28/2019 Aceton Plant

    18/25

    How does the team know the cost willbe this much?

    What has been the cost trend foracetone in the past?

    How much of a loss will be avoided?

    How do you know?

    In regard to the previous slide:

  • 7/28/2019 Aceton Plant

    19/25

    3) Produce 97.6% Acetone

    Need to add 3 heat exchangers

    Renegotiate deal?

    Break-even point

  • 7/28/2019 Aceton Plant

    20/25

    In regard to the previous slide:

    What about the break-evenpoint?

    What would it cost to produce

    acetone at this purity?

    Is that purity acceptable?

    What is this slide telling us aboutthe option?

    What do these three bulletpoints have in common?

  • 7/28/2019 Aceton Plant

    21/25

    Recommendations

    Buy acetone off open market

    Dissolve acetone production facility

    Recover maximum amount of lost $$

  • 7/28/2019 Aceton Plant

    22/25

    Conclusions

    Adjustment of property package identifiedseparation difficulty

    Possible solutions Extractive distillation

    Purchase acetone on the open market

    Renegotiate contract for lower acetone purity

    Purchase acetone on open market is best

  • 7/28/2019 Aceton Plant

    23/25

    In regard to the previous slide:

    Why put the conclusion after therecommendation?

  • 7/28/2019 Aceton Plant

    24/25

    TAKE AWAY POINTS

    After viewing this PowerPointWhat are yourtake-away lessons thatyou will apply to your own PowerPointnext time?

  • 7/28/2019 Aceton Plant

    25/25

    This team puts its conclusions at the end and didnot use informative headings on its process flowdiagrams. The headings do not outline the

    argument.

    A pitch that presented the recommendation firstand gave evidence of calculations to support

    claims would have been more persuasive.The PPT cant reinforce the oral message orpersuade readers on its own.

    For more help:Making Logical Technical Arguments PPT; TeamPresentations in Chemical and Biomolecular Engineering PPT

    Notes