HÜTTE Bohrtechnik GmbH - Ziegeleistraße 36 - D-57462 Olpe/Biggesee Germany - Tel: +49 (0)2761 96440 - E-mail: [email protected] Casagrande S.p.a. - Via A. Malignani, 1 - 33074 Fontanfredda (Pn) Italy - Tel: +39 (0)434 9941 - E-mail:[email protected] Job Report www.casagrandegroup.com August – September 2014 HBR 609 THE PROJECT Contractor: Geotech Foundation Solutions B.V. (GFS), Netherlands Master of works: Groningen Seaports B.V. Location: Eemshaven Netherlands Project description: Construction of wharfage - Beatrixhaven fase 5 – Eemshaven Niederlande Equipment: Hütte HBR 609 Job description The new construction of the wharfage consists of a combined wall made of tubes, Ø 1.820 mm and 37 to 40 m long, together with sheet piles PU-20, 27 m long. To support the combined wall, GFS has drilled self-drilling- bolts as follows: 86 pieces of self-drilling-bolts 117/64 with a casing crown Ø 350 mm and up to a single length of 52 to 63 m 7 pieces self-drilling-bolts 103/62 with a casing crown Ø 300 mm and up to a single length of 42 to 45 m Design was developed by GFS in accordance with the latest standards and Eurocodes. Examination of anchors was carried out with a test load of 200 to 325 tons. A Hütte HBR 609 was used together with a drill mast type DM260 and a hydraulic hammer type Eurodrill HD8032. Handling of cases was done with a hydraulic double acting manipulator HDM 89-220. This manipulator has a range for drilling pipes Ø 89-220 mm with a single length of 2 to 6 m.

Geotech Niederlande HBR 609 GB - Hütte Bohrtechnik

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Geotech Niederlande HBR 609 GB - Hütte Bohrtechnik

HÜTTE Bohrtechnik GmbH - Ziegeleistraße 36 - D-57462 Olpe/Biggesee Germany - Tel: +49 (0)2761 96440 - E-mail: [email protected] Casagrande S.p.a. - Via A. Malignani, 1 - 33074 Fontanfredda (Pn) Italy - Tel: +39 (0)434 9941 - E-mail:[email protected]

Job Report

www.casagrandegroup.com August – September 2014

HBR 609

THE PROJECT Contractor: Geotech Foundation Solutions B.V.

(GFS), Netherlands

Master of works:

Groningen Seaports B.V.

Location: Eemshaven Netherlands

Project description:

Construction of wharfage -

Beatrixhaven fase 5 – Eemshaven

Niederlande

Equipment: Hütte HBR 609

Job description The new construction of the wharfage consists of a

combined wall made of tubes, Ø 1.820 mm and 37 to

40 m long, together with sheet piles PU-20, 27 m long. To

support the combined wall, GFS has drilled self-drilling-

bolts as follows:

• 86 pieces of self-drilling-bolts 117/64 with a casing

crown Ø 350 mm and up to a single length of

52 to 63 m

• 7 pieces self-drilling-bolts 103/62 with a casing crown

Ø 300 mm and up to a single length of 42 to 45 m

Design was developed by GFS in accordance with the

latest standards and Eurocodes.

Examination of anchors was carried out with a test load

of 200 to 325 tons.

A Hütte HBR 609 was used together with a drill mast

type DM260 and a hydraulic hammer type Eurodrill

HD8032. Handling of cases was done with a hydraulic

double acting manipulator HDM 89-220. This

manipulator has a range for drilling pipes Ø 89-220 mm

with a single length of 2 to 6 m.